Prep course · $1,800 Free reference Certifications

PMP Earned Value Management: every formula, one page

The 11 earned value formulas the PMP exam tests — each with what it means, how to read the result, and a single worked example that ties them all together.

Advertisement · 728×90

Start with the four base terms

Every earned value calculation is built from four numbers. Get these right and the rest is arithmetic.

  • PV — Planned Value: budgeted cost of the work scheduled by now. PV = BAC × planned % complete
  • EV — Earned Value: budgeted cost of the work actually done. EV = BAC × actual % complete
  • AC — Actual Cost: what you have actually spent to do that work.
  • BAC — Budget at Completion: the total approved budget for the project.
The trick that unlocks everything

Every formula begins with EV. Variances subtract; indexes divide. Anything about cost pairs EV with AC; anything about schedule pairs EV with PV. That single sentence reproduces the whole table below.

All 11 formulas

MetricFormulaMeaningGood result
Variances — subtract
CV Cost VarianceEV − ACAre we under or over budget?Positive = under budget
SV Schedule VarianceEV − PVAre we ahead of or behind schedule?Positive = ahead
Indexes — divide
CPI Cost Perf. IndexEV ÷ ACValue earned per $1 spent> 1.0 = under budget
SPI Schedule Perf. IndexEV ÷ PVProgress vs plan> 1.0 = ahead
Forecasts
EAC Estimate at CompletionBAC ÷ CPI (typical)Expected total cost if current performance holds≤ BAC
EAC (atypical)AC + (BAC − EV)If the variance was a one-off≤ BAC
EAC (cost & schedule)AC + (BAC − EV) ÷ (CPI × SPI)When both slippages persist≤ BAC
ETC Estimate to CompleteEAC − ACCost still remainingAs planned
VAC Variance at CompletionBAC − EACForecast budget surplus / overrunPositive = surplus
TCPI (to hit BAC)(BAC − EV) ÷ (BAC − AC)Efficiency needed to finish on the original budget≤ 1.0 = achievable
TCPI (to hit EAC)(BAC − EV) ÷ (EAC − AC)Efficiency needed to finish at the new forecast≈ 1.0

Percent complete: % complete = EV ÷ BAC.

Advertisement · In-feed

Reading the numbers in one breath

  • Variances: negative is bad, positive is good. CV < 0 = over budget; SV < 0 = behind schedule.
  • Indexes: below 1.0 is bad, above 1.0 is good. CPI 0.9 = you spend $1 to earn 90¢ of value.
  • Memory hook: if the term ends in Variance you subtract; if it ends in Index you divide. Cost → AC, Schedule → PV.

Worked example

A project has BAC = $100,000, scheduled to be 50% done by today. It is actually 40% complete, and you have spent AC = $60,000.

  • PV = 100,000 × 0.50 = $50,000
  • EV = 100,000 × 0.40 = $40,000
  • CV = EV − AC = 40,000 − 60,000 = −$20,000 → over budget
  • SV = EV − PV = 40,000 − 50,000 = −$10,000 → behind schedule
  • CPI = EV ÷ AC = 40,000 ÷ 60,000 = 0.67 → 67¢ earned per $1
  • SPI = EV ÷ PV = 40,000 ÷ 50,000 = 0.80 → 80% of planned pace
  • EAC = BAC ÷ CPI = 100,000 ÷ 0.67 ≈ $149,300 → forecast overrun
  • VAC = BAC − EAC ≈ 100,000 − 149,300 = −$49,300

Verdict: this project is both over budget and behind schedule, and at the current rate will finish roughly 49% over budget unless performance improves.

Mistakes examiners test

  • Mixing up the index direction. Below 1.0 is always bad — students often invert it under time pressure.
  • Using AC where PV belongs. Schedule metrics (SV, SPI) use PV, never AC.
  • Choosing the wrong EAC. Read whether the variance is described as typical (use BAC ÷ CPI) or a one-off (use AC + (BAC − EV)).
  • Forgetting SV and SPI are in cost units. Earned value measures schedule in dollars of work, not in days.

Sources

  1. Project Management Institute — PMI.org.
  2. PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), earned value management.
  3. PMI, The Standard for Earned Value Management.

Summary for study reference only. "PMP", "PMBOK" and "PMI" are marks of the Project Management Institute, which does not endorse this material.