Interactive tool Free Certifications

Earned value (EVM) calculator

Enter the four base numbers — BAC, PV, EV and AC — and get every PMP earned value metric: cost and schedule variances, performance indexes, all three EAC forecasts, ETC, VAC and TCPI, each with what the result means. Computed in your browser; nothing is sent anywhere.

Advertisement · 728×90
earned-value-calculator no data leaves your browser

PV = BAC × planned % complete · EV = BAC × actual % complete. Enter all four in the same currency.

The four inputs

Every earned value calculation is built from four numbers. Get these right and the rest is arithmetic.

  • BAC — Budget at Completion: the total approved budget for the project.
  • PV — Planned Value: budgeted cost of the work scheduled by now. PV = BAC × planned % complete
  • EV — Earned Value: budgeted cost of the work actually done. EV = BAC × actual % complete
  • AC — Actual Cost: what you have actually spent to do that work.
Reading the results

Variances (CV, SV): positive is good, negative is bad. Indexes (CPI, SPI): above 1.0 is good, below 1.0 is bad. Cost pairs EV with AC; schedule pairs EV with PV.

Which EAC does the tool show?

There are three estimate-at-completion formulas, and the exam tests whether you pick the right one. The calculator shows all three; ETC and VAC are derived from the typical EAC (BAC ÷ CPI), the most common exam default.

  • TypicalBAC ÷ CPI — current cost performance continues.
  • One-offAC + (BAC − EV) — the variance was a one-time event; remaining work runs at budgeted rate.
  • Cost & scheduleAC + (BAC − EV) ÷ (CPI × SPI) — both slippages persist.

TCPI — the efficiency you still need

The to-complete performance index tells you how efficiently the remaining work must be done. TCPI to hit BAC = (BAC − EV) ÷ (BAC − AC); if it is above 1.0, finishing on the original budget requires better performance than you have managed so far — often a sign the budget is no longer realistic.

Sources

  1. Project Management Institute — PMI.org.
  2. PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), earned value management.
  3. PMI, The Standard for Earned Value Management.

Reference tool only. "PMP", "PMBOK" and "PMI" are marks of the Project Management Institute, which does not endorse this material.