Prep course · $1,800 Free reference Certifications

PMP estimation: four techniques and the PERT formulas

Analogous, parametric, bottom-up and three-point estimating — when to use each, plus the triangular and beta (PERT) formulas with standard deviation.

Advertisement · 728×90

Four estimating techniques

TechniqueHow it worksAccuracy / effort
Analogous (top-down)Use a similar past project's actuals + expert judgement.Fast, least accurate
ParametricStatistical: rate × quantity (e.g. $50/m² × 200 m²).Accurate if data is good
Bottom-upEstimate each work package, then sum.Most accurate, most effort
Three-pointCombine optimistic (O), most likely (M), pessimistic (P).Accounts for uncertainty

Three-point formulas (PERT)

QuantityFormula
Triangular (simple average)(O + M + P) ÷ 3
Beta / PERT (weighted)(O + 4M + P) ÷ 6
Standard deviation(P − O) ÷ 6
Variance((P − O) ÷ 6)²

Example: O=8, M=10, P=18 → PERT = (8 + 40 + 18) ÷ 6 = 11; std dev = (18 − 8) ÷ 6 ≈ 1.67.

Estimate accuracy ranges

  • Rough Order of Magnitude (ROM): −25% to +75% (early).
  • Definitive estimate: −5% to +10% (later, more detail).

Mistakes examiners test

  • Using triangular when asked for PERT. PERT weights the most likely value 4×.
  • Std dev with /3. Standard deviation uses (P − O) ÷ 6.
  • Analogous = accurate. It's the fastest but least accurate.

Test yourself

4 quick questions — tap an answer to check it instantly. Nothing is sent anywhere.

1. The PERT (beta) estimate weights which value 4×?

Answer: B. PERT = (O + 4M + P) ÷ 6 — the most likely estimate is weighted four times.

2. Standard deviation of a three-point estimate is…

Answer: A. Std dev = (Pessimistic − Optimistic) ÷ 6.

3. Which technique is fastest but least accurate?

Answer: C. Analogous (top-down) uses a similar past project — quick, but least accurate.

4. Parametric estimating is based on…

Answer: B. Parametric uses a unit rate × quantity, e.g. $50/m² × 200 m².

Sources

  1. Project Management Institute — pmi.org.
  2. PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide).

Study summary only. "PMP" and "PMBOK" are marks of the Project Management Institute, which does not endorse this material.